Projekt

Standort
Cologne
Besonderheiten & Herausforderungen
1. Installation of a textile roof (solar shading)
- Solar shading system: A wave-form tensioned, non-combustible textile shading structure (silver PTFE-coated glass fabric) is erected above the inner tower core.
- Steelwork & tensioning frames: This involves installing a hot-dip galvanised and powder-coated supporting structure in section steel (S355), together with 15 made-to-measure tensioning frames onto which the fabric has already been fixed at the works.
2. Construction of a new storage room
- Steel structure: Construction of a new, frost-proof ancillary room within the widened tower core, used to store the mobile catering furniture.
- Roof & walls: Installation of a trapezoidal sheet roof connected to the existing drainage, together with insulation cassettes and a discreet facade-integrated flush door (“jib door”).
- Due diligence: As the concrete floor slab contains water-bearing heating coils below the surface, the drilling points for the columns must be located precisely beforehand.
3. Dismantling and adaptation work on the facade
- Dismantling: The existing steel frame structure on the tower core is completely removed and disposed of.
- Facade refurbishment (art concept): 15 existing aluminium facade cassettes are removed without damage, stripped at the works, re-powder-coated and repainted as part of a special art concept.
- Reinstallation: Following the conversion and floor-coating work, the refurbished sheets and new sheets for the storage room are refitted.
4. Logistics and site set-up (working at height)
- Transport routes: As the site is more than 100 metres above ground, logistics are strictly regulated. Material is transported primarily via the goods lift up to the event floor and from there via a special telescopic hoist to the upper storey.
- Lifting equipment: For bulky components (such as the 4.35 m tensioning frames), a cable hoist with a jib system is set up on the platform to raise material from outside.